Weapon Systems Acquisition Reform Act Of 2009—Conference Report

Sen. John McCain

legislator photo

Mr. President, the majority leader requested that I begin the discussion on the conference report for the Weapon Systems Acquisition Reform Act of 2009. We await the presence of the chairman of the Armed Services Committee. I begin by thanking him for his leadership, his really nonpartisan addressing of this compelling issue.

The last time I was on the floor, I talked a lot about the terrible cost overruns that were associated recently with literally every new weapon system we have acquired. When I tell some of my constituents and friends, they are staggered by the numbers--a small littoral combat ship that is supposed to cost $90 million ends up costing $400 million and has to be scrapped; airplanes costing, depending on how you look at it, half a billion dollars each.

Working together on both sides of the aisle, and under the leadership of Chairman Levin, we have come up with legislation that has gone through the Congress rather rapidly.

I would also like to say that the President of the United States called us, Members of the House, leaders of the Armed Services Committees, to the White House, where we pledged our support and our rapid addressing of this challenge.

The only thing more important than the substance of this conference report is the demonstration of bipartisanship that went into how the underlying bills were created and guided through the legislative process.

As I said, I know the chairman of the committee is going to be here shortly, and he will discuss many of the specific aspects of this bill. But it does emphasize starting major weapons systems off right by having those systems obtain reliable and independent cost estimates and subjecting them to rigorous developmental testing and systems engineering early in their acquisition cycle. It does a lot of things. As I say, Senator Levin will enumerate many of them.

What we are trying to do is address a process where there is a need for a weapon system which takes years to develop. Technical changes are incorporated time after time in a desire--and a laudable one--to reach 100 percent perfection. But then the cost overruns grow and grow.

The Future Combat Systems, an Army innovation to address conflicts of the future, was supposed to cost $90 billion. It is up to $120 billion. Even more, we still do not have operational vehicles. So, very appropriately, the Secretary of Defense announced that he would be eliminating much of this program to try to get the costs under control.

I would like to say a word about the Secretary of Defense, who has agreed to continue to serve this country under one of the most difficult and trying positions one can have in Government. The Secretary of Defense has announced, I think very appropriately, that we would be reducing and eliminating some programs that have maybe had a good reason for a beginning but certainly have had such incredible cost overruns that they no longer are a worthwhile expenditure of the taxpayers' dollars.

Early in the first couple of weeks of the new administration, a group of us attended a gathering. The President of the United States and I had an exchange about the Presidential helicopter. Some years ago, we decided the Presidential helicopter, which is 30 years old, needed replacement. We finally reached a point where we had not built one completely yet, and it was more than the cost of Air Force One--you cannot make that up; it is hard to believe--as one technological change after another was piled on, to the point where neither the President nor the Secretary of Defense felt it was worth the cost. The President does need a new helicopter. We need to embark on that effort. But what we just went through should be an object lesson, and we should learn from the lessons and cost overruns.

I note the presence of the distinguished chairman of the Armed Services Committee in the Chamber. I again thank him for his leadership.

I yield the floor.

The Senator from Michigan.

Sen. Carl Levin

legislator photo

Mr. President, I am pleased to join with Senator McCain in bringing to the floor the Weapon Systems Acquisition Reform Act. We introduced this bill. We did it on February 23, I believe, and we did it to address some of the problems in the performance of the Department of Defense major defense acquisition programs at a time when growth and cost overruns on these programs have simply reached levels which are unaffordable, unsustainable, and unconscionable, in some cases. Since that time, the bill has made rapid legislative progress.

I thank Senator McCain for all he has done. This was a bipartisan effort. Our colleagues on the Armed Services Committee worked out the differences that existed, and we unanimously recommended it to the Senate. But the magnitude of this problem is such that we must move quickly on it. The President has asked us to get the bill to his desk by Memorial Day, and it is our hope we will be able to do that.

On May 7, the bill passed the Senate unanimously. A week later, a companion bill passed the House. We worked out the differences between the Senate and the House in record speed. The ability to do this was based on the working relationship which has been built up here. We work on a bipartisan basis in the Armed Services Committee. We work on a bicameral basis with the House and the Senate. When it comes to issues of national security, particularly, we are able to act so quickly.

I publicly thank not only Senator McCain, as I have, and colleagues of ours on the Armed Services Committee, but also Chairman Ike Skelton and John McHugh of the House Armed Services Committee.

This is a tremendously important bill. It has major reforms. It is going to address some of the most persistent underlying problems we have had that led to the failure of defense acquisition programs. What are those problems? The Department relies too often on unreasonable cost and schedule estimates. Second, too often the Department insists on unrealistic performance expectations. Third, the Department too often uses immature technologies. Fourth, too often the Department adopts these very costly changes to program requirements, to production quantities, and to funding levels right in the middle of the ongoing program.

The conference report I hope we will be able to consider in the next few minutes is going to address these problems in the following ways:

First, we provide for a strong new Senate-confirmed Director of Cost Assessment and Program Evaluation. That person is going to report directly to the Secretary of Defense to ensure that defense acquisition programs are based on sound cost estimates. The independence of that office is new, and it is essential. That person goes directly to the Office of the Secretary of Defense, not as the situation is now where there is a level of bureaucracy between the cost estimator and assessor and the Secretary of Defense.

Second, we require the Department to rebuild systems engineering and developmental testing organizations and capabilities which have been almost dismantled or reduced significantly. We want to ensure that design problems are understood and addressed early in the process.

Third, we establish mechanisms to ensure early tradeoffs are made between cost, schedule, and performance objectives so that we do not overcommit to what the Secretary of Defense has called ``exquisite'' program requirements.

Fourth, we require the increased use of competitive prototyping so that we select the best systems and prove they can work before we start building them.

Fifth, we establish new requirements for continuing competition.

Sixth, we address the problem of organizational conflicts of interest to ensure we get the best possible results out of the defense industry.

Seventh, we require regular program reviews and root cause analyses to address developing programs in acquisition programs.

Finally, we establish tough new Nunn-McCurdy requirements, so-called. We put teeth in the Nunn-McCurdy approach. We establish a presumption of program termination and the requirement that continuing programs be justified from the ground up to ensure we do not throw good money after bad on failing programs. If a program is failing, now it is too easy to get by the Nunn-McCurdy test of continuing a program. It is going to be a lot harder to jump that hurdle should programs be failing in the middle or costing a lot more or taking a lot longer.

So we have a strong bill. It is going to help change the acquisition culture of the Department of Defense, and it is going to point our acquisition system in the direction it needs to go. We hope Members of the Senate will join us in supporting this effort and send the bill to the President for his signature.

Our staff has done extraordinary work, particularly Peter Levine and Creighton Greene on my staff, and Chris Paul and Pablo Corrillo on Senator McCain's staff. And, again, I thank all Members and the leadership for bringing this bill, pushing it along, and giving us the encouragement and support that is so essential to get a bill of this magnitude to the floor of the Senate in record time.

Mr. President, I yield the floor, and I suggest the absence of a quorum.

The clerk will call the roll.

The legislative clerk proceded to call the roll.

Sen. Richard J. Durbin

legislator photo

Mr. President, I ask unanimous consent that the order for the quorum call be rescinded.

Without objection, it is so ordered.

Sen. Richard J. Durbin

legislator photo

Mr. President, I ask unanimous consent that the Senate now proceed to the conference report to accompany S. 454 and vote immediately on adoption of the conference report; that upon adoption of the conference report, the Senate then resume consideration of H.R. 2346 and the McConnell amendment No. 1136, as modified by the Levin language to the McConnell amendment, with the time equally divided and controlled between Senators McConnell and Durbin or their designees; that upon disposition of the McConnell amendment, the Senate then proceed to vote in relation to the Brownback amendment No. 1140, as modified; that prior to the first and third vote, there be 2 minutes of debate equally divided and controlled in the usual form; that after the first vote in this sequence, the succeeding votes be 10 minutes in duration, with no amendments in order to the amendments in this agreement.

Without objection, it is so ordered.

Under the previous order, the Senate will proceed to the consideration of the conference report to accompany S. 454. The report will be stated.

The bill clerk read as follows:

The committee of conference on the disagreeing votes of the two Houses on the amendment of the House to the bill (S. 454) to improve the organization and procedures of the Department of Defense for the acquisition of major weapon systems, and for other purposes, having met, after full and free conference, have agreed to recommend and do recommend to their respective Houses this report, signed by a majority of the conferees.

The Senate will proceed to the consideration of the conference report.

(The conference report is printed in the House proceedings of the Record of today, May 20, 2009.)

Sen. Susan Collins

legislator photo

Mr. President, the Weapon Systems Acquisition Reform Act of 2009 would strengthen and reform the Department of Defense acquisition processes by bringing increased accountability and transparency to major defense acquisition programs. Simply put, the bill would build discipline into the planning and requirements process, keep projects focused, help prevent cost overruns and schedule delays, and ultimately save taxpayer dollars.

I would like to thank Senators Carl Levin and John McCain, and Representatives Ike Skelton and John McHugh for their work on this important issue and their continued efforts to improve procurement at the Department of Defense. I was proud to join Senators Levin and McCain in co-sponsoring this bill in the Senate.

This legislation would improve DOD's planning and program oversight in many ways. First, the bill would create a new Senate-confirmed Director of Independent Cost Assessment and Program Evaluation to be the ``principal cost estimation official'' at the Department.

The bill also mandates that the Department carefully balance cost, schedule, and performance as part of the requirements development process, building discipline into the procurement process long before a request for proposals is issued or a contract is awarded.

I applaud the ``bright lines'' this legislation would establish regarding organizational conflicts of interest by DOD contractors. These reforms would strengthen the wall between government employees and contractors, helping to ensure that ethical boundaries are respected. While contractors are important partners with military and civilian employees at DOD, their roles and responsibilities must be well defined and free of conflicts of interest as they undertake their critical work supporting our Nation's military.

I appreciate the conferees including an amendment that I offered on the floor with Senator Claire McCaskill regarding earned value management, EVM. EVM provides important visibility into the scope, schedule, and cost of a program in a single integrated system, and when properly applied, EVM can provide an early warning of performance problems.

GAO has observed that contractor reporting on EVM often lacks consistency, leading to inaccurate data and faulty application of the EVM metric. In other words, garbage in, garbage out.

The conference report would require that the Department of Defense issue an implementation plan for applying EVM consistently and reliably to all projects that use this project management tool.

The implementation plan would also provide enforcement mechanisms to ensure that contractors establish and use approved EVM systems and require DOD to consider the quality of the contractor's EVM systems and reporting in the past performance evaluation for a contract. With improved EVM data quality, both the government and the contractor will be able to improve program oversight, leading to better acquisition outcomes.

The conference report would strengthen the Department's acquisition planning, increase and improve program oversight, and help prevent contracting waste, fraud, and mismanagement. Ultimately, it will help ensure that our military personnel have the equipment they need, when they need it, and that tax dollars are not wasted on programs that were doomed to fail.

Sen. Richard J. Durbin

legislator photo

Mr. President, the Weapons Systems Acquisition Reform Act of 2009 takes steps in the right direction to reform the way the Department of Defense buys major weapons systems.

When it comes to these multi-billion-dollar systems, the challenges of managing acquisitions are tremendous.

Officials at the Department of Defense manage 96 major defense acquisition programs--the Department's most expensive programs.

Each program costs hundreds of millions of dollars to research and develop and billions of dollars more to purchase. Together, these programs account for $1.6 trillion in defense spending.

These major defense acquisition programs have seen a shocking growth in cost. Over the last 20 years, the costs of these programs have ballooned by $296 billion.

Costs especially exploded during the previous administration. Since 2003, the cost of major defense acquisition programs rose by $113 billion.

The Weapons Systems Acquisition Reform Act of 2009 takes important steps to bring this spending under control, without compromising on the quality of the systems purchased.

This is not the first time Congress has tried to reform the defense acquisition process. Nor will it likely be the last. But it is an important step at a critical time.

The legislation would create an independent director of cost assessment who would verify the estimated cost of a program before allowing it to go forward.

It builds in additional checkpoints to help make sure that programs are ready on time.

It enhances the R&D capabilities at the Department of Defense. Numerous studies have found that the R&D capabilities of the Army, Navy, and Air Force are in desperate need of strengthening.

It requires defense contractors to build a strong wall between their R&D and construction offices when both offices work on the same defense project.

Finally, it gives combatant commanders more authority to procure products that meet the immediate needs of troops in theater.

Secretary Gates has been rightly frustrated with the inability of the regular procurement process to field equipment, like MRAPs, that are needed immediately by troops on the ground. This legislation will help change that.

I commend Senators Levin and McCain for their leadership in developing this thoughtful and needed legislation. I look forward to its being signed into law by President Obama.

There is now 2 minutes of debate equally divided prior to a vote on the adoption of the conference report.

Sen. Carl Levin

legislator photo

Mr. President, both Senator McCain and I spoke on this matter. I ask unanimous consent to yield back all remaining time. I think I can do this with the consent of Senator McCain.

Without objection, it is so ordered.

The question is on agreeing to the conference report.

Sen. Carl Levin

legislator photo

Mr. President, I ask for the yeas and nays.

Is there a sufficient second?

There appears to be a sufficient second.

The clerk will call the roll.

The bill clerk called the roll.

Sen. Richard J. Durbin

legislator photo

I announce that the Senator from West Virginia (Mr. Byrd), the Senator from Massachusetts (Mr. Kennedy), and the Senator from West Virginia (Mr. Rockefeller) are necessarily absent.

I further announce that if present and voting, the Senator from West Virginia (Mr. Rockefeller), would vote ``yea.''

Sen. Jon Kyl

legislator photo

The following Senator is necessarily absent: the Senator from Utah (Mr. Hatch).

Are there any other Senators in the Chamber desiring to vote?

The result was announced--yeas 95, nays 0, as follows:

[Rollcall Vote No. 197 Leg.] YEAS--95 Akaka Alexander Barrasso Baucus Bayh Begich Bennet Bennett Bingaman Bond Boxer Brown Brownback Bunning Burr Burris Cantwell Cardin Carper Casey Chambliss Coburn Cochran Collins Conrad Corker Cornyn Crapo DeMint Dodd Dorgan Durbin Ensign Enzi Feingold Feinstein Gillibrand Graham Grassley Gregg Hagan Harkin Hutchison Inhofe Inouye Isakson Johanns Johnson Kaufman Kerry Klobuchar Kohl Kyl Landrieu Lautenberg Leahy Levin Lieberman Lincoln Lugar Martinez McCain McCaskill McConnell Menendez Merkley Mikulski Murkowski Murray Nelson (NE) Nelson (FL) Pryor Reed Reid Risch Roberts Sanders Schumer Sessions Shaheen Shelby Snowe Specter Stabenow Tester Thune Udall (CO) Udall (NM) Vitter Voinovich Warner Webb Whitehouse Wicker Wyden NOT VOTING--4 Byrd Hatch Kennedy Rockefeller

The conference report was agreed to.

Sen. Richard J. Durbin

legislator photo

I move to reconsider the vote by which the conference report was adopted.